MIRP New Road Access  ( 19/00002/FUL )  30/01/2020

We are pleased to announce to have received detailed Planning Consent to connect Mossend International Rail Freight Park ( MIRP ) to the Trunk Road Network

 

MIRP Bids for London Heathrow Expansion Hub

Tender Documents were submitted to LHR on the 27/01/20, the basis of our bid was to maximise the use of Rail Transport to move the pre constructed material from Scotland to LHR, helping to reduce carbon emission from the supply chain by use of Electric Locomotives.

 

August 2019  – December 2019  Engineering Earthworks for New Rail Access

Good progress has been made to form the Rail Access and phase 1 is now complete and the compaction criteria has exceeded . We are now ready to receive the material to construct the infrastructure sidings ( 2 x 650m )

 

July 2019 Commencement of John G Russell Intermodal Rail Service from Mossend to Daventry

The successful transfer of these two daily trains ( 12 trains per week) has been supported  by the purchase of two new Reach Stackers ( Hyster RS46-33IH ).

 

June 2019 First Anniversary of Peel Ports Intermodal Rail Service from Seaforth ( Liverpool ) to Mossend

This Intermodal Rail Service has gone from strength to strength supporting Scotland’s export growth and reducing and decarbonising the supply chain.